Six years on from devastating blaze, why has the Steeple not risen from the ashes?

placeholder image

INCREDIBLY, almost six years has now passed since flames tore through one of Antrim’s most beloved buildings. In less than seven hours, almost two centuries of local history went up in smoke.

INCREDIBLY, almost six years has now passed since flames tore through one of Antrim’s most beloved buildings.

In less than seven hours, almost two centuries of local history went up in smoke.

The first flames were spotted licking from the roof of Steeple House at 5.20am on July 2 2019 and within minutes two appliances were roaring to the scene from Antrim Station - later joined by a third from Ballymena and a turntable ladder and aerial hose from Belfast.

Despite the suffocating smoke and searing heat, the firefighters battled to bring the blaze under control - eventually declaring victory shortly after 12 noon.

The fire, they said, was started intentionally. This was a mindless act of arson, and the impact was utterly devastating.

Smoke still chuffed from the eves as the Fire Service withdrew.

The ferocious flames had consumed everything in their path, leaving little more than the four walls.

The ceiling had collapsed and the grand staircase was no more.

The floor had gone too, exposing the cavernous basement beneath.

Walls that had once been adorned by artwork were scorched back to bare stones.

Intricate cornice work that harked back to the grand house’s former glory were lost forever.

Even the colour of the building seemed to have changed in its death throes, the familiar green somehow sooty and pale.

A regal mansion which had stood for centuries was reduced to a smoldering skeleton.

It was a truly dreadful spectacle, but doubly so for the council staff who had worked there until the move to the new Civic Centre in 2005.

For them, thoughts of the old house are filled with warm memories of the people who once inhabited it - characters like Jack Allen, Paddy Marks, Bobby Loughran, Sam Magee and Ron Woods, often with trademark cigarette in hand.

Now those corridors and offices were gone.

Some immediately called for a rebuild, but it was clear that this would be a mammoth task.

Indeed, some felt that the more likely outcome was to retreat and then quietly demolish it when the structural integrity worsened. After all, that was what happened to Antrim Castle five decades ago.

But on the first anniversary the council confirmed that they were still weighing up the options for the Steeple - and a rebuild still seemed to be on the table.

“The Council has engaged with its insurers and we have a project team in place to produce a specification for the reinstatement of the building,” said a spokesman.

“Progress has been impacted by COVID-19, but last week specialist heritage architects visited the site to make a technical assessment as part of this project.”

In time, the council’s insurers paid up, and there were indications that the money would be ploughed back into the Steeple.

Conservation architects would be involved in the project, they said, sensitively restoring the building - with adaptions for improved access.

Ultimately, it would once again be a space for the people of Antrim, used for conferences and community events.

That was the plan, anyway. But the initial flurry of announcements has yet to translate into significant action.

Quite a contrast to July 2021, when the council enthusiastically backed the restoration of the Grade B+ listed building - with Planning Committee vice-chair Fraser Agnew saying that the vote of confidence would safeguard the house and park for generations to come.

“I am delighted that the plans approved by the Committee this evening will secure this important part of our local heritage,” he said.

“The plans ensure that Steeple House will be restored to its pre-fire condition, respecting the character, architecture and historic interest of the building.

“The planning proposal also received support and was commended by the Historic Environment Division, the Department responsible for listed buildings in Northern Ireland.”

And the announcements kept on coming.

In March 2022 it was reported that works were expected to begin by the end of the year. By that summer there was mounting speculation that they were on the brink of securing £1 in funding for the Steeple project. Things seemed to be moving, at last.

In February 2024 funding of over £343,000 was awarded by the Heritage Fund to help council progress plans to apply for a full National Lottery grant to redevelop Steeple Park.

It was thought that if all went to plan, the council could secure over £3.5m for the project.

So where are we at now?

A council spokesperson has revealed this week that it may still be some time before they ‘get the builders in’.

Yes, four long years after the Planning Committee gave the restoration the thumbs up it seems that the project is now officially in limbo with some key decisions yet to be made.

“The Steeple Park and House Project is included in the Council’s Capital Programme,” said a spokesperson this week.

“This project business case is being developed to understand the preferred option based on community and cultural needs, affordability, and sustainability.”

So when - or indeed if - Steeple House will rise from the ashes is anyone’s guess...